Network
fundamentals:
Networks are composed
of events and activities as defined below:
Event:
An event is defined as the starting or ending
point of an activity or a group of activites. It represents a milestone
and does not consume time or resources. Event is described by a circle
(o). Activity:
Activity:
is
the work required to proceed from one event to another It consumes therefore
time and resources. It is represented by an arrow(->)
- To draw network diagram an interdependencies
between events and activites must be identified so that master plan
can be developed which illustrate the up-to-date picture of operations
during the project.
- Network analysis provides valuable
information for planning, integration of plans, time scheduling ,
and resource management.
- The primary purpose of network is
to eliminate crisis management by providing a pictorial representation
of the total program from which the time estimates such as Early starting
time(EST) and Late starting time(LST) and their impact can be made.
Network Rules:
- Each
activity must have a preceding and a succeeding event
- Each
Event should have a distinct(unique) number.
- There
should not be loop in the project network as shown below:
- Note More than one activity can have
the same preceding and succeeding event
- Any
number of activities may merge with an event.
Network
Development
1.Enmurate all those activities in
the Project which needs close monitoring to complete them in time.
2.Define each activity as
Preceding activity(the activity which preceed it).
Succeding activity(the activity which followed).
Concurrent activity(the activity that can be done concurrently)
3.Estimation of time for the completion
of each activity.
The
estimation of time for the completion of each activity is important in
the network analysis. This can be done using three possible assumptions.
I. Optimistic time(a):
This
time assumes that every thing will go accordingly to with minimum a
mount ofdifficulties and such situation may occur approximately 1 percent
of time.
II. Most pessimistic
time(b):
This
time assumes that every thing will not go according to plan and that the
maximum potential difficulties will develop and may occur approximately
one percent of time.
III. Most likely or normal time(m):
This
is the time that would most often occur should this effort be reported over
over again.
The
estimated time of the completion of an activity is given by:
te= (a+4m+b)/6
Where
te = estimated time
a =
most optimistic time
m = normal
time
b = most pessimistic
time
Standard
Devation
Standard
devation of the estimated time(te):
sd
(te) = (b-a)/6
|